Spring 2019

  • Draft Compliance Report
  • Contact external consultants to review Compliance Report
  • Conduct internal review cycles
  • Develop Quality Enhancement Plan (QEP)
  • Feb. 18-21, 2019: Observe on-site peer review team at Chowan University, NC (Private, Level III)

Summer 2019

  • Complete draft of compliance report
  • Continue internal review cycles
  • Compliance Report based on University input
  • Develop QEP

Fall 2019

  • Sept. 10: Compliance Report due
  • Conduct internal review cycles on the QEP
  • Oct. 10: Submit nomination and accompanying biographical information to be considered for Lead QEP Evaluator (6 months prior to on-site visit)
  • Revise the QEP based on University input
  • Complete QEP by November
  • Prepare for off-site peer review
  • Nov. 5-8: off-site peer review
  • Develop a Focused Report, as needed

Spring 2020

  • Feb. 5-6: Advisory Visit
  • March 2: Submit the QEP and Focused Report (6 weeks before the on-site visit)
  • April 13-16: Host the on-site peer review team
  • Begin implementing QEP

Summer 2020

  • Begin preparing any responses to the on-site peer review team

Fall 2020

  • Sept. 16: Formally respond to review by the on-site peer review team
  • Dec. 8-11: Prepare for review by SACSCOC Board of Trustees
  • Continue implementing QEP

Spring 2021

  • Receive official letter of accreditation (i.e. Action Letter) from SACSCOC Board of Trustees in January